Ribbon Cutting Ceremony for the Lorton Road Widening Project

ATCS was present at the Ribbon Cutting Ceremony for the Lorton Road Widening Project at the Barrett House this past Thursday, March 30th, 2017. ATCS was the Design Firm of Record for preliminary design through construction. Pictured, Thomas Fleming (6th from left) who lead the design construction phase services.

Ribbon Small

 

ATCS is a professional consulting firm providing comprehensive services in transportation planning and design, engineering, traffic engineering, environmental, water resources, water/wastewater, disaster planning, response and recovery efforts, construction management and inspection, and surveying. ATCS prides itself in high standards for quality, business ethics, and concerns for the communities in which it lives and works. This is a vital component of the firm’s mission and vision. For more information follow us on Facebook, Twitter and LinkedIn

Media Contact
Leslie Thomas
703.430.7501 x188
lthomas@atcsplc.com

carlsivler-tran

Carl D Silver Parkway Roadway, Storm Drainage and Utility Improvements City of Fredericksburg, Virginia

ATCS provided comprehensive engineering design services for preliminary through final design of the Carl D Silver Parkway project located in the City of Fredericksburg, Virginia. ATCS performed all roadway design and civil engineering services from the initial alignment studies through the submission of construction documents. This roadway consisted of two (2) phases with the following elements:

  • 6,000 linear feet of four (4)-lane closed section roadway with a varying width MS-2 raised grass median
  • 2,900 linear feet of six (6)-lane closed section roadway also with a MS-2 raised grass median
  • 1,110 feet of two (2)-lane closed section roadway
  • Approximately 16,000 feet of waterlines
  • Approximately 4,400 feet of sanitary sewer
  • Approximately 10,400 linear feet of storm sewer
  • Nine (9)-way utility duct bank
  • Six (6) stormwater management basins
  • Four (4) bioretention filters design for low impact development
  • 211 linear feet of 16-foot-wide by 5-foot-high Con-Span for a significant water crossing.

The roadway was designed to VDOT standards and was accepted into the VDOT state system of highways. The project also featured VDOT approved pavement design, signing, and pavement marking plans. The project also featured multiphase erosion and sediment control plans meeting DCR requirements with specifically designed sediment basins and other E&S control measures. Maintenance-of-traffic concerns were minor since this was a new road. To prepare final construction plans, a detailed and thorough Roadway Alignment Study was first performed. This study led to the final alignment that was eventually built.